Home Project

AstraZeneca | Power Reliability Upgrades

Gaithersburg, MD

Project Overview

Heffron partnered with AstraZeneca on a four-year, phased power reliability upgrade at the company’s occupied United States headquarters in Gaithersburg, MD — a mission-critical campus that could not afford an outage during construction.

Phase 1 installed a 2.5-megawatt Combined Heat and Power (CHP) plant comprised of a natural gas generator and a heat recovery steam generator. The scope included a significant site-work package to construct a cast-in-place exterior concrete mechanical yard to house the equipment.

Phase 2 consolidated the eight-building campus — originally fed by four separate utility feeds — onto a single electrical switchgear lineup serving more than 1,000,000 square feet of occupied space. Two dedicated underground 13.8 kV feeders were installed from the campus back to the utility substation, and new paralleling gear was added to control the CHP alongside the two pre-existing 3-megawatt diesel emergency generators.

Phase 3 added a second 2.5-megawatt CHP, a 500-ton absorption chiller, and a supporting cooling tower — giving the site the ability to recover waste heat from the CHP and generate cooling from it. The completed system gives AstraZeneca the ability to carry the entire campus electrical load on 11 megawatts of on-site generation, dramatically reduce boiler use by producing high-pressure steam from the heat recovery steam generators, and pull heating hot water from the engine cooling loops. The result is a technically complex system that protects ongoing operation of a mission-critical campus while delivering a significant environmental impact reduction.

Project Details

Client

AstraZeneca

Location

Gaithersburg, MD (1,000,000+ SF campus)

Sector

Life Sciences

Duration

Four-year, three-phase delivery in occupied space

On-site Generation

Two 2.5 MW CHP units + two 3 MW diesel generators (11 MW total)

Mechanical / Electrical Scope

CHP + heat recovery steam generators · 500-ton absorption chiller + cooling tower · 13.8 kV underground feeders · Paralleling switchgear · Cast-in-place mechanical yard

Project Gallery

On-site at AstraZeneca Power Reliability Upgrades.

Have a similar project?

Let's talk about what you're building.

Heffron self-performs mechanical construction across the Mid-Atlantic — including inside active, validated production facilities.

AstraZeneca | 700 Progress Way

Gaithersburg, MD

Project Overview

A full-building lease at 700 Progress Way — recognized as Maryland’s Best Lease of 2024 — anchors AstraZeneca’s expanding Gaithersburg manufacturing footprint. Heffron self-performed the mechanical scope that converted this 197,645-square-foot facility into production-ready space, installing the chilled water plant, high-purity process piping, and base-loaded pump skids that keep a cGMP biological operation running without interruption.

The work sits within a relationship that already spans the company’s MedImmune Way campus and 200 Orchard fit-out — one continuous standard of execution across every AstraZeneca address in Montgomery County. 

Project Details

Client

AstraZeneca

Location

Gaithersburg, MD

Size

197,645 SF

Sector

Life Sciences

Recognition

Maryland's Best Lease of 2024

Mechanical Scope

Chilled water plant · High-purity process piping · Base-loaded pump skids · cGMP utility distribution

Delivery

Self-perform mechanical (weld, fab, install)

Project Gallery

On-site at AstraZeneca 700 Progress Way.

Have a similar project?

Let's talk about what you're building.

Heffron self-performs mechanical construction across the Mid-Atlantic — including inside active, validated production facilities.

AstraZeneca | ADC Laboratory Expansion

Gaithersburg, MD

Project Overview

To support expanding capabilities at the MedImmune Way campus, Heffron self-performed the mechanical scope on AstraZeneca’s Antibody Drug Conjugate (ADC) Laboratory expansion — a project that more than doubled the size of the existing ADC space and reorganized the layout for maximum operational efficiency.

The defining challenge was keeping the existing lab running uninterrupted for all but a single two-week shutdown, during which the new exhaust systems were tied into the existing exhaust and live operations were relocated into the newly expanded space. Heffron then renovated the original lab in place.

Heffron’s mechanical scope included a fully welded stainless steel exhaust duct system, twelve flow hoods, a self-contained vacuum system, lab gases, casework integration, and airlocks — all delivered with the precise sequencing required to protect active research throughout construction.

Project Details

Client

AstraZeneca

Location

Gaithersburg, MD

Sector

Life Sciences

Project Type

New laboratory build + adjacent renovation

Architect / Engineer

WB Engineers + Consultants

Mechanical Scope

Welded stainless steel exhaust duct · 12 flow hoods · Self-contained vacuum system · Lab gases · Airlocks · Casework integration

Delivery

Self-perform mechanical with single 2-week tie-in shutdown

Campus Gallery

Recent work across MedImmune Way

Have a similar project?

Let's talk about what you're building.

Heffron self-performs mechanical construction across the Mid-Atlantic — including inside active, validated production facilities.

AstraZeneca | Campus Cafeteria Renovation

Gaithersburg, MD

Project Overview

AstraZeneca’s US headquarters campus cafeteria received a full renovation and expansion to 17,000 SF, allowing the site to serve nearly 6,000 employees and offer a broader range of healthier dining options. Adjacent conference rooms and hotel suites were demolished to enlarge the kitchen footprint and open up new seating capacity.

Heffron self-performed the mechanical scope behind the build-out — new HVAC distribution throughout the seating area, a stainless steel kitchen exhaust duct system with condensate drains routed through occupied areas of the building, and a new dedicated exhaust fan serving the dishwasher station.

Mechanical scope also supported a new 23′ × 11′ walk-in refrigerator with integrated blast chiller, a new dishwasher station, and the relocation of an existing freezer. The defining challenge was keeping the existing cafeteria open and serving employees throughout construction — coordination, phasing, and after-hours tie-ins protected daily food service from start to finish.

Project Details

Client

AstraZeneca

Location

Gaithersburg, MD

Sector

Life Sciences

Size

17,000 SF cafeteria · serves ~6,000 employees

Architect

Jacobs

Mechanical Scope

HVAC distribution · Stainless steel kitchen exhaust duct + condensate drains · Dishwasher exhaust fan · Walk-in refrigerator/blast chiller hook-up · Freezer relocation

Delivery

Self-perform mechanical with cafeteria fully operational throughout

Project Gallery

On-site at AstraZeneca Campus Cafeteria Renovation.

Have a similar project?

Let's talk about what you're building.

Heffron self-performs mechanical construction across the Mid-Atlantic — including inside active, validated production facilities.

Client Portfolio

AstraZeneca | MedImmune Way

AstraZeneca’s MedImmune Way headquarters is one of Heffron’s longest-running, most technically demanding partnerships — an occupied 1,000,000+ square-foot campus housing labs, pilot plant, vivarium, small- and large-scale manufacturing, and corporate space.

Heffron has supported the site through new laboratory build-outs, AHU and fume hood replacements, high-purity water systems, equipment installations, and a multi-year power reliability upgrade — all delivered without interrupting the science.

Campus Gallery

Recent work across MedImmune Way

Partner with Heffron

Trusted on AstraZeneca's most demanding campus

From new laboratory build-outs to mission-critical power reliability, Heffron self-performs the mechanical scope behind AstraZeneca’s most complex Maryland sites.

AstraZeneca | 200 Orchard

Gaithersburg, MD

Project Overview

Part of Heffron’s ongoing mechanical work across the AstraZeneca campus, the 200 Orchard project covers full mechanical scope inside an active life-sciences environment — primary hot and chilled water distribution with full pipe insulation and jacketing, process piping, sanitary waste, vent, and fixture rough-in (including Geberit wall-hung carriers), ductwork, and rooftop York air-cooled chiller installation, tie-ins, startup, and commissioning. Every line is identified and labeled to the campus standard so facilities staff can trace and service the system on day one.

Heffron crews welded, fabricated, and installed pipe and equipment alongside in-house planning and coordination with AstraZeneca facilities staff. The work reflects the standard the client expects on this campus: precise execution in occupied space, with safety and quality treated as non-negotiable.

On 200 Orchard, Heffron worked as a true extension of the general contractor’s team — owning the mechanical scope end-to-end, hitting the schedule, and keeping the GC out of the weeds on coordination, submittals, and field issues. That’s the way we partner with every GC or client we work with: predictable execution, clean handoffs, and no surprises on the punch list.

Project Details

Client

AstraZeneca

Location

Gaithersburg, MD

Sector

Life Sciences

Mechanical Scope

Hot & chilled water distribution · Process & plumbing piping · Ductwork · Rooftop York chiller installation & tie-ins

Delivery

Self-perform mechanical (weld, fab, install)

Project Gallery

On-site at AstraZeneca 200 Orchard.

Have a similar project?

Let's talk about what you're building.

Heffron self-performs mechanical construction across the Mid-Atlantic — including inside active, validated production facilities.

Client Portfolio

GSK Campuses

Rockville, MD

Heffron has delivered mechanical construction across one of Maryland’s most significant life-sciences campuses in Rockville — from the original 650,000-square-foot research headquarters built for Human Genome Sciences to follow-on work supporting the site’s later use as a global vaccines R&D center under GSK.

The campus has since passed through three major biopharma owners, a testament to the lasting quality of the facilities Heffron helped build.

Partner with Heffron

Bring us into your next life sciences scope

From early design assist through startup and commissioning, Heffron self-performs the mechanical scope your team can build a schedule around.

Project Overview

Heffron has supported NIH Shady Grove with mechanical construction in a live federal research environment where reliability, coordination, and schedule discipline are foundational to the work. The campus combines laboratory, administrative, and technical spaces — the kind of mixed-use government setting where mechanical scope has to perform cleanly from day one.

The project sits squarely inside Heffron’s wheelhouse: institutional work with research-level expectations, active occupancy, and stakeholders who need a contractor that can coordinate across disciplines without creating drag on the broader build.

Project Details

Client

National Institutes of Health

Location

Rockville, MD

Sector

Government, Life Sciences

Project Type

Federal research campus mechanical construction

Have a similar project?

Let's talk about what you're building.

Heffron self-performs mechanical construction across the DMV — Washington D.C., Maryland, and Virginia — including inside active, validated production facilities.

Project Overview

Heffron has delivered mechanical scope across MilliporeSigma’s Maryland life sciences operations, tying new equipment into live research and manufacturing environments without interrupting production.

The work spans the full utility backbone of the site — from rooftop heat rejection down through the central plant and out to validated process rooms — keeping cooling, high-purity water, and clean utilities reliable for sensitive research and biomanufacturing workloads.

Heffron continues to service the building today. What started as a build relationship is now an ongoing service partnership — the same crews who installed the cooling towers, chillers, high-purity water systems, and central plant equipment are back on site keeping it running years later. That’s the Heffron model: build it right the first time, then stay with the client to maintain it for the life of the facility.

Scope of Work

01

Rooftop cooling towers and condenser water — evaporative cooling towers set by crane, with adjacent air handlers and ductwork reworked to suit the new heat-rejection layout.

02

Chilled water distribution — primary chilled water and CHW return piping routed through the facility and tied into mechanical room equipment and controls.

03

High-purity and process water systems — multi-vessel filtration, softening, and DI trains, plus skid-mounted process water packages with PLC-driven controls feeding lab and production points of use.

04

Central utility plant — pressure vessels, expansion and storage tanks, heat exchangers, and hot-water generation, installed and tied into existing site utilities.

05

Cleanroom process equipment — stainless steel pass-through autoclave set and connected to steam, water, drain, and exhaust within a validated cleanroom envelope.

06

Mechanical service and detail work — overhead piping, valve stations, and utility-corridor build-out supporting the broader scope.

07

Ongoing service — Heffron's service division continues to maintain the facility today, the same team that built it.

Project Details

Client

MilliporeSigma

Location

Maryland

Sector

Life Sciences

Engagement

Build + ongoing service — Heffron still services the building today

Project Gallery

On-site at United Therapeutics GMP Therapy Production Facility.

United Therapeutics United Therapeutics — view 2

Project Gallery

On-site at MilliporeSigma.

Have a similar project?

Let's talk about what you're building.

Heffron self-performs mechanical construction across the DMV — Washington D.C., Maryland, and Virginia — including inside active, validated production facilities.
Photo Credit: WBJ

Client Portfolio

Novavax Projects

Gaithersburg, MD

Heffron has supported Novavax’s growing life sciences footprint in Gaithersburg through work connected to laboratory, clinical, office, and GMP environments.

Across these projects, the work required careful coordination in active facilities, support for specialized lab infrastructure, and reliable mechanical and plumbing systems designed to serve critical research and operational needs.

Partner with Heffron

Bring us into your next life sciences scope

From early design assist through startup and commissioning, Heffron self-performs the mechanical scope your team can build a schedule around.